top of page

Create Your First Project

Start adding your projects to your portfolio. Click on "Manage Projects" to get started

City of Houston East Water Purification Plants 1, 2 & 3

Past Projects

EWPP: Plant 3 Sedimentation Basin Clarifier Drives and Mechanisms and Electrical Conduits Replacement

EWPP: Installation of Vertical Flocculators at Plant 3, Implementation of Energy Optimization Tool at Plant 3, Transfer Pump Station and Other Improvements at Plants 1, 2 and 3

EWPP: Chlorine System Improvements - Replace Wet Scrubbers with Dry Scrubbers

EWPP: Chlorine Systems Improvements Package 2 - Ton Containers, Evaporators, Chlorinators, Ejectors, Piping & Misc Improvements

EWPP: Emergency Filter Repair

Active Projects

EWPP: Plants 1 & 2 Replacement of Valves and Actuators at High Service Pump Station

EWPP: Chlorine System Improvements Package 3 - Railcar Building Conversion to Chlorine Storage Building and Life Safety System Improvements

Industrial TX has completed a series of major upgrades and improvements at the East Water Purification Plant for the City of Houston.

Key Accomplishments:
- Installation of New Clarifier Mechanisms at Plant 3 as well as structural improvements
- Installation of New Vertical Flocculators at Plant 3 as well as structural improvements
- Replacement of the Chlorine Wet Scrubbers with Dry Scrubbers at Plants 1, 2 & 3 Chlorine Buildings
- Complete Demolition and Replacement of the Chlorine System at Plants 1, 2 & 3, Including New Chlorine Piping, Chlorine Evaporators, Chlorinators, Injectors, and Improvements to the Chlorine Ton Container Building
- Emergency Repairs to all 36 Gravity Filters at Plants 1, 2 & 3

Ongoing Work:
- Replacement of Large Valves and Actuators at the Plant 1 & 2 High Service Pump Station
- Conversion of the Railcar Buildings into Chlorine Ton Cylinder Storage at Plants 1, 2 & 3 as well as Life Safety System Improvements

bottom of page